Highway Improvement Project
Highway Improvement Project – Additional Traffic Lanes Construction on Highway No. 212,
Control Section 0102, Pak Suay – Nam Pe Section
This project involved the contracted construction activities to enhance highway efficiency by adding traffic lanes on Highway No. 212 between Km. 44+570 and Km. 46+100, covering a total length of approximately 1.530 kilometers at one location.
Contract No.: NK.27/2024
Project Duration: May 16, 2024 – November 11, 2024
Project Value: 47,672,945.00 Baht
Contracting Authority: Department of Highways, Ministry of Transport
Project Location: Nong Khai Province